Restoration Project

Suzuki RE-5 1975

Presented by redbug2


Pictures


Early Picture of complete bike with original carriers on.Early Picture of complete bike with original carriers on.A beginning....A beginning....Cover off, decided to powder coat turn signal stems.Cover off, decided to powder coat turn signal stems.Front Forks.Front Forks.Right Side.Right Side.
Ouch! A mouse nest!Ouch! A mouse nest!Carb Cleaned enough to start it up on the primary, still need to fix accelerator pump channel...Carb Cleaned enough to start it up on the primary, still need to fix accelerator pump channel...Cleaning mouse poop out of air filter.Cleaning mouse poop out of air filter.Air filter rehabbed after mouse nest, only a few more pop rivets to go.Air filter rehabbed after mouse nest, only a few more pop rivets to go.Mufflers a little rusty.Mufflers a little rusty.
Needs some cleaningNeeds some cleaningRear rack, it must come off...Rear rack, it must come off...Rusty Fender BottomRusty Fender BottomAcid wash to halt the rusting.Acid wash to halt the rusting.Re5 cover after 1500 grain paper and some aluminum polishRe5 cover after 1500 grain paper and some aluminum polish
Compressing the rear shock in the vise.Compressing the rear shock in the vise.Loosening the lock nut.Loosening the lock nut.ApartApartSanding the springSanding the springSanded, now, powder coat or cad plate?Sanded, now, powder coat or cad plate?
Chrome getting cleaned up.Chrome getting cleaned up.More chrome cleaningMore chrome cleaningTire off, lots of grease to remove.Tire off, lots of grease to remove.Rear of engine, still some more to go and painting to do.Rear of engine, still some more to go and painting to do.Batter box in great need of a coating. Used gloss black powder coat.Batter box in great need of a coating. Used gloss black powder coat.
Came out nice, happy with the resultsCame out nice, happy with the resultsBattery box in bike.Battery box in bike.Still Cleaning.Still Cleaning.Cleaning up everything I can get to. This was black with grease, you could not see the color on the wires before cleaning.Cleaning up everything I can get to. This was black with grease, you could not see the color on the wires before cleaning.Kick Stand on... My first piece added after taking it apart!Kick Stand on... My first piece added after taking it apart!
Fort pegs, on cleaned and cad plated and one not.Fort pegs, on cleaned and cad plated and one not.Another ViewAnother ViewCad plated hardware.Cad plated hardware.Before Power WashingBefore Power WashingEngine after power washing.Engine after power washing.
Left side as the assembly continuesLeft side as the assembly continuesRight SideRight SideRadiator OnRadiator OnWiring and frame cleaned up.Wiring and frame cleaned up.Radiator PaintedRadiator Painted
Air Intake PolishedAir Intake PolishedDry fit of the remaining parts.Dry fit of the remaining parts.Guage unit paintedGuage unit paintedGuage unit paintedGuage unit paintedRe5-1Re5-1
RE5-2RE5-2RE5-3RE5-3RE5-4RE5-4RE5-5RE5-5RE5-6RE5-6
RE-5 7RE-5 7889910101111
1212RimRimReplaced rim.Replaced rim.Building Tire Truing stand 1Building Tire Truing stand 1Building Tire Truing stand 2Building Tire Truing stand 2
Building Tire Truing stand 3Building Tire Truing stand 3New Cleaned up and cad coated shockNew Cleaned up and cad coated shockNew HornNew HornTire off of another RE5, spokes were better but needed a lot of cleanup.Tire off of another RE5, spokes were better but needed a lot of cleanup.Ready for show.Ready for show.
New Front and Rear tires on.New Front and Rear tires on.In a show.In a show.Many People Admiring it at the show.Many People Admiring it at the show.Front view at show.Front view at show.In front of showroom.In front of showroom.
Old post on left. New posts from stainless steel.Old post on left. New posts from stainless steel.Back on the bike.Back on the bike.

Restoration Journal

Work completed, time invested, expenses, and lessons learned.

Finish Air Filter

Date not recorded
Hours spent3.0
Recorded cost$20.00
Work performed / notes

<p>Cleaned and reassembled air filter.Purchased a great filter from Rotary Recycle. Bought new pop rivet gun to rivet cover back on. </p>

Unloaded Bike.

Started 2009-10-23 , Finished 2009-10-23
Hours spent3.0
Recorded cost$0.00
Work performed / notes

<p>After a few months of anticipation, the bike arrived. My brother-in-law and I decided to try and get it to run... Placed battery in machine and it did turn over.. Cleaned points and did get spark... Took off air filter cover and noticed that carb was home to a mouse. </p><p>Cleaned carb and also cleaned up front turn signals. Bike needs a lot&nbsp;of cleaning.. Hopefully cleaned carb will start it up... </p>

Got it running!

Started 2009-10-25 , Finished 2009-10-25
Hours spent3.0
Recorded cost$0.00
Work performed / notes

<p>Took carb off again and re-checked all ports after reading the manual... A few jets were clogged... Still have a clogged accelerator pump passage, unable to remove jet... Will have to come up with a solution... Let it run and drove it up and down the driveway, seems to run well, digital gear readout is working... </p>

Rebuilt purchased carb

Started 2009-11-11 , Finished 2009-11-11
Hours spent2.0
Recorded cost$0.00
Work performed / notes

Rebuilt the carburetor I had purchased from ebay. It was not that bad, the usual hardened gas in the bowl. Soaked it in the carb cleaner bucket. Removed all of the jets first. After soaking blew out all of the ports. Just took the jets I had cleaned from my original carb and used those. It started up fine and ran OK. Still needs some tuning. Idles nice.Boy, it really runs hot, those pipes a super hot.

Cleaned mouse nest from Air Filter

Started 2009-11-15 , Finished 2009-11-15
Hours spent2.0
Recorded cost$0.00
Work performed / notes

<p>Had to dissasemble air filter by drilling out right side pop rivets... Was full of filler from mouse nest, also had a dead mouse inside.... Still cleaning... </p><p>&nbsp;Tested oil injection pump by taking line off of carb and plugging carb hole. Started bike and the oil was pumping out, will stop running pre-mix.&nbsp; </p><p>&nbsp;Cleaned some more rust off of chrome.&nbsp; </p>

Cleaned a little more.

Started 2009-11-22 , Finished 2009-11-22
Hours spent1.0
Recorded cost$0.00
Work performed / notes

Did some more cleaning. Also got bike running again, needs a lot of cleaning...

6 work entries14.0 total hours$20.00 recorded costs

To Do Entries

Total Cost: $20.00    Total Hours: 14


Parts Wanted
Name
Category
Desired Cost
Date Entered
Part Description